Sources: Hungary considering replacing Rosatom in nuclear power project – Reuters

Hungary is considering replacing Russia’s Rosatom as the main supplier for the expansion of the Paks nuclear power plant and has begun examining alternative suppliers. Reuters reports this, citing two sources.

The project, which was originally estimated to cost 12.5 billion euros, has so far cost Hungary more than 2 billion euros. Of this, around 1.1 billion euros has been paid to Rosatom.

The government is expected to decide on the project’s future at the end of the year or the beginning of next year.

According to one of the sources, the government is leaning towards carrying out the expansion, but without Rosatom’s involvement. However, changing suppliers could entail additional costs and contractual legal complications.